On Wednesday I spent 2.25 hours on the windows and got the living room trim up. I have to buy a nail driver because contractor curiously didn't drive nails and left them sticking out about a half an inch.

On Thursday, my only progress was to run out and get the get nail driver (half hour)

I also threw down 8 more bags of chips in the yard - I'm thinking maybe 8 bags every other month for maintenance.

On Friday, I spent half an hour prepping and redoing my schedule. It's ambitious in terms of what I want to accomplish in each coat, but it reduces the number of remaining coats from 6 to 4.

I've spent 273 hours to date on the windows.